Tuesday, June 30, 2015

June 30

Buildings & Grounds personnel will be fertilizing the fields near the blockhouse today. Dust may interfere with the painting of exterior walls so we will work on the inside.

Thursday, June 25, 2015

June 25


  • Garage door wall is completely painted.
  • We will apply hydraulic cement on holes in the exterior walls and finish painting the entrance wall.
Priming the back wall.
Garage door area painted.





Wednesday, June 24, 2015

June 24

Goals
  • Finish priming the exterior walls of the blockhouse.
  • Start painting the exterior walls.

Tuesday, June 23, 2015

June 23

Due to the foreseen weather, we will be priming the inside of the blockhouse.

Monday, June 22, 2015

June 22

We'll be priming all day.

The prime we use on the walls are transparent; therefore, when it dries, the appears completely clear. We have to take pictures to keep track of what has already been primed (and proof that we worked at all). We used painter's tape to mark where we left off.







We purchased samples of the colors we are going to use for the blockhouse and tested it on a primed section of the wall.

Bernard advertising Pepsi.

Thursday, June 18, 2015

June 18


Activities
  • Apply Primer on the front exterior wall.
  • We were going to apply primer to the interior walls, but we purchased the wrong roller.
  • We need to fill holes on the front wall with hydraulic cement before priming.
The crew at work.